Projects
- Home
- Projects
Projects implemented in 2023.
Delivery of boiler evaporator parts for The Unit 7
Delivery of boiler evaporator parts for The Unit 7
Disassemble and assemble of steam pipelines
Reconstruction of the boiler in The Unit 6 – TPP…
Construction of a gas boiler room with two boilers of 10 MW each
Construction of a gas boiler room with two boilers of…
Projects implemented in 2022.
Production and delivery of ribbed pipe supports
Production and delivery of ribbed pipe supports RIBBED PIPE…
Production and assembly of the DCB column
Production and assembly of the DCB column Procurement of…
Overhaul of the Clean petroleum fuel terminal
Total overhaul of the Clean petroleum fuel terminal Blažuj Mechanical…
Replacement of the panel of ascending part of the boiler
Replacement of the panel of ascending part of the boiler…
Overhaul of the Thermal Power Plant Stanari
Installation of evaporation panels on the water walls of the…
Projects implemented in 2021.
Installation of hot pipeline gas boiler with following equipment and burner
Delivery and installation of hot pipeline gas boiler with following…
Installation of the steam pipe of the intermediate superheated steam of the boiler unit 7
Installation and supervision of the installation of the steam pipeline…
Procurement and installation of high-pressure heater (HPH) 1 in Unit 7
Procurement and installation of high-pressure heater 1 in Unit 7…
Construction of a gas boiler room
Construction of a gas boiler room Construction and commissioning…
Construction of inside infrastructure for compressing and preparation for shipping of natural gas
Construction of inside infrastructure for compressing and preparation for shipping…
Projects implemented in 2020.
Replacement of a new inlet hood, inlet pipeline system with compensator and thermal insulation
Agglomeration – AMZ Replacement of a new inlet hood, inlet…
Installation of the boiler drum in The Unit 7
Installation of the boiler drum in The Unit 7 Dismantling…
Installation of mechanical equipment for the transportation system
Installation of mechanical equipment for the transportation system Placing the…
Projects implemented in 2019.
Replacement of the electrostatic precipitator filter with a hybrid filter
Replacement of the electrostatic precipitator filter with a hybrid filter…
Replacement of condenser tube TYPE 300-KCS-4
Capital overhaul – engine room of the main object of…
Other projects completed between 2007 and 2018
THERMAL POWER PLANTS
M&TPP UGLJEVIK
Project details
- Replacement of the electrofiltration system
- VALUE: 587.447
- 2017
- 90 days
Project description
Reconstruction and replacement of the electrofiltration system
NEXT PROJECT
Project details
- Capital overhaul
- VALUE: 2.300.813
- 2010
- 90 days
Project description
- Replacement of economizer ECO I and ECO II
- Replacement of water blowers
- Design and replacement of recirculation channels
- Design and installation of thermal insulation on recirculation channels
- Installation of fluxometers
M&TPP GACKO
Project details
- Capital overhaul
- VALUE: 726.380
- 2012
- 117 days
Project description
- Overhaul of flaps on air ducts
- Pipe system renewal
- Overhaul - replacement of pipes in the utility boiler room
- Overhaul - replacement of the convective steam superheater
- Overhaul - replacement of curtain panel steam superheaters
- Reconstruction of combustion chamber ventilation
NEXT PROJECT
Project details
- Boiler reconstruction
- VALUE: 815.183
- 2004
- 90 days
Project description
- Boiler reconstruction
TPP Kakanj
Project details
- Replacement of the sixth superheater on the fifth boiler, Unit 5th
- VALUE: 199.266
- 2013
- 211 days
Project description
- Replacement of the sixth superheater on the fifth boiler, as well as work on disassemble other components
- Replacement of connected pipes MP2
- Ceiling repair works on the superheater and intermediate superheater of Unith 5th
- Procurement and installation of burners on the fifth boiler
NEXT PROJECT
Project details
- Overhaul of the furnace marked as 31 F 01
- VALUE: 2.157.115
- 2011
- 305 days
Project description
- Boiler reconstruction in Plant Unit 6th
- Welded over 18.000 welds on the pressured part of the boiler
- Disassembled 1.726.350 kilos of boiler equipment and assembled 1.232.777 kilos of new boiler equipment for pressured and non-pressured parts of the boiler
TPP Tuzla
Project details
- Boilers pipe system repair
- VALUE: 41.982
- 2015
- 107 days
Project description
Overhaul of parts of the pipe system on the boilers from Plant Units 3rd, 4th, 5th and 6th
NEXT PROJECT
Project details
- The fifth boiler economizer
- VALUE: 500.000
- 2010
- 105 days
Project description
Disassemble and assemble of the economizer on the fifth boiler
NEXT PROJECT
REFINERIES
OIL REFINERY BROD
Project details
- Capital overhaul
- VALUE: 280.555
- 2014
- 75 days
Project description
- Connection of supply pipelines to tank M-1
- Disassemble of damaged and assemble of new tube bundles on tube exchangers marked as 31-E-13 and 31-E-03
NEXT PROJECT
Project details
- Capital overhaul and funnel reconstruction
- VALUE: 330.077
- 2011
- 90 days
Project description
- Preparation and lifting of the second, third and fourth section of the convection of spiral tube and bracing of the supporting structure of furnace marked as 31-F-01, section number 31
NEXT PROJECT
OIL REFINERY MODRIČA
Project details
- Repair works on tanks, steam pipes and exchangers
- VALUE: 750.000
- 2010
- 21 day
Project description
- Rehabilitation of tanks and steam pipelines
- Disassemble, washing and assemble of exchangers marked as 11-E05 A&B and 11-E03 A&B
- Thermal insulation of the tank marked as 61-T-01
- Assemble and disassemble of the first scaffold, anti-corrosive protection of the tank marked as 61-T-01
- Repair of the exchanger marked as 30-E-23
NEXT PROJECT
Project details
- Welding works
- VALUE: 150.000
- 2009
- 45 days
Project description
- Welding of pipelines and reinforcement construction of base oil and paraffin facilities
HYDROELECTRIC POWER PLANTS
HYDROPOWER PLANTS GRABOVICA AND MLEČVA
Project details
- Pipeline installation
- VALUE: 72.663
- 2017
- 132 days
Project description
- Installation of the pipelines at Mlečva HPP Ø610x4, 2.350 m, 180 pcs. 13 m each
- Installation of the pipelines at Grabovica HPP Ø813x5, 1.540 m, 117 pcs. 13 m each
- Inspection of welded joints at Mlečva HPP and Grabovica HPP
HYDROPOWER PLANT CRKVINA
Project details
- Installation of the pipeline to the turbine
- VALUE: 30.677
- 2016
- 60 days
Project description
- Pipeline installation works Ø760x4.5 and Ø711x4.5; Weight 158.000 kilos
- Production of custom shaped pieces (57 pcs.)
- Radiographic control of welded joints
- Waterproofing of welded joints
- Hydrostatic pressure testing of pipelines
HYDROPOWER PLANT GOVZA, FOČA
HYDROPOWER PLANT ON TREBIŠNJICA RIVER
Detalji projekta
- Capital overhaul
- VALUE: 84.746
- 2010
- 160 days
Opis projekta
- Capital overhaul of the turbine part of the engine HPP Trebišnjica
- Drainage pumps repair and refurbishment
ArcelorMittal Zenica
Project details
- Capital overhaul
- VALUE: 1.560.000
- 2017. - 2018.
- 360 days
Project description
- Production, delivery and installation of pipes for oxygen, natural gas and other equipment, according to the specification.
- Assemble of the Blooms equipment for enrichment of the technical air for Salem furnace
- Overhaul of the first and the second boiler in Steel plant (replacement of the economizer and moving parts of the boiler)
- Overhaul, disassemble and assemble of Taret LF and CCM in Steel Plant
- Machine works on the casting platform and CCM bunker in Steel Plant
- Construction of access staircase for Taret LF in Steel Plant
- Disassemble and assemble of pumps (three pieces) in MC Wire Rode Mill
- Production and assemble of an oxygen ramp
- Disassemble and assemble of the radiator valve reducer on the PS4
- Rehabilitation of the facility on the Blast furnace casting platform
- Rehabilitation of the Cowper stove in the Blast furnace
- Machine works MPRM third phase
- Production and replacement of part of the pipeline Ø3225 mm electro filter No. 6 exhaustor tube side
NEXT PROJECT
Project details
- Boiler reconstruction
- VALUE: 559.580
- 2007
- 120 days
Project description
- Reconstruction of the K-2 boiler
Gas pipeline
GAS PIPELINE Šepak
Project details
- Gas pipeline Šepak – Bijeljina
- Energotehnika Južna Bačka
- VALUE: 633.424
- 2018
- Approx 180 days
Project description
Machine and assemble works on the construction of Šepak – Bijeljina pipeline gas route.
NEXT PROJECT
Project details
- Pipeline installation
- Sarajevo gas
- VALUE: 11.000
- 2011
- 25 days
Project description
Pipeline installation over the bridge in Vojkovici
Natron-Hayat Maglaj
Project details
- Disassemble and assemble of the economizer
- VALUE: 20.792
- 2016
- 30 days
Project description
Disassemble and assemble of the finned tubes on the economizer.
Bimal Brčko
Project details
- Disassemble and assemble works
- VALUE: 160.000
- 2017
- 70 days
Project description
- Disassemble and assemble and alteration of tanks, including constituent supporting structures and pipelines
- Disassemble of five inox tanks, location Loznica Srbija
- Disassemble of two tanks, as well as assemble and alteration of three inox tanks, location Industrial complex BIMAL Brčko
NEXT PROJECT
Project details
- Overhaul
- VALUE: 15.000
- 2010
- 25 days
Project description
- Overhaul of the pressing and boiler room
THE ALUMINIUM PLANT Podgorica
PETROCHEMICAL PLANT KIRISHI - RUSSIAN FEDERATION
HEATING PLANT Bosanski Brod
Project details
- Construction of the heating plant according to the turn-key system
- VALUE: 1.350.811
- 2007
- 12 months
Project description
- Construction of the heating plant, according to the turn-key system
Aktuelna gradilišta u BiH